Manor House AAP previous stages
What has been the AAP process so far?
Stage 1: Scoping and Baseline
This stage concluded with the production of the Manor House AAP Baseline Report which consists of background supporting material and provides an initial 'evidence base' upon which the Plan was developed.
Hackney has produced and commissioned a series of studies and background evidence which provide information to support production of the Hackney Local Development Framework (LDF). You can view these on the LDF evidence page.
Stage 2: Initial issues and opportunities
A Masterplan Vision and Objectives were developed which were used to guide the formulation of a number of AAP Options. The Options were tested through the Sustainability Appraisal, viability assessment and discussion with stakeholders.
Stage 3: Preparation of Consultation Draft Manor House AAP (Phase 1) - Masterplan
Following the assessment of initial community engagement in early 2010 of issues and options, this Area Action Plan represents the most appropriate strategic framework taken forward (when compared to the alternatives, it provided the most potential for wider regeneration improvements) and the AAP developed into a consultation draft document with input from stakeholders.
Stage 4: Consultation (Regulation 25)
The Draft AAP (Phase 1) underwent extensive formal public consultation for 10 weeks between September - December 2010.
- Draft Manor House Area Action Plan (Phase 1) Masterplan - Draft for Public Consultation (PDF, 7.5MB)
Stage 5: AAP
Consultation responses were assessed following the consultation period and the AAP was revised in consideration of responses where appropriate. Please find a link to the consultation database below.
- Manor House AAP Consultation Database (including a schedule of respondents) (PDF, 197KB)
- Manor House AAP Statement of Consultation (PDF, 294KB)
Stage 6: Publication (Regulation 27) and Representations relating to the AAP (Regulation 28)
The current stage of AAP Production is Publication where public representations on the soundness and legal compliance of the AAP can be made within a 6 week period.
Following consideration by Cabinet in July 2011, the Council formally approved the Area Action Plan (Pre-Submission document) for Regulation 27 Publication.
Public representations were invited within a 6 week period from Wednesday 21 September until Thursday 3 November on the soundness and legal compliance of the AAP.
Stage 7: Submission to Secretary of State (Regulation 30) - Current Stage
The AAP, supporting documents and representations have been submitted to the Secretary of State on the 30 April 2011 and will be subsequently be subject to examination with the 'tests of soundness'. You can view information on the current stage here.
Page updated: 4 May 2012